Respuesta :
Answer:
d. Sequential task
Explanation:
A sequential task is an activity that can only begin after another activity, called the predecessor or the activity being evaluated, has finished. It means you must wait for the predecessor to complete before starting the sequential task. This ensures that the activities are performed in a specific order or sequence, where each task depends on completing the previous one. Sequential tasks help maintain a logical flow and prevent any conflicts or issues arising from starting an activity before its prerequisites are met.
Final answer:
The correct term for an activity that can start only after the prior task finishes is a 'Successor'. This is an essential concept in project management for scheduling and planning.
Explanation:
The correct answer to the question is a. Successor. In the context of project management and scheduling, a successor activity is one that cannot start until the preceding task, known as the predecessor, is completed. Successor activities are often mapped out in project management tools such as Gantt charts, which visually represent the sequence and dependencies of tasks within a project. Understanding the relationship between predecessor and successor tasks is crucial for effective project planning and timely project completion.