A project manager has two engineers assigned to the project and does not have access to more even if the result means extending the completion date on the project. The project manager is managing a(n) ________.

Respuesta :

The project manager is managing a Resource-constrained project.

Resource-constrained project is one where the availability of assets is restricted. If the resources are not able to complete on time, the project gets delayed and there is no opportunity to get additional resources. The resource can be machine, device, human, etc. In this situation, as the handiest engineers are available, it is a resource-constrained project.

Humans, substances, and devices are all considered resource constraints. If any of these are restricted in that there aren't sufficient to finish the activities they're scheduled for in the amount of time given, the timing and collection of sports inside the assignment network can be impacted.

The shortage of resources finally ends up determining how you pass about your work, which generally leads to resource overloading. essentially, this means you spend an excessive amount of time working on these projects and stretch out your workdays to compensate for the resource constraints.

Learn more about constraints here brainly.com/question/6073946