If Dominik completes a project by himself, it will take him 8 hours. Working with Katarina, it will take them 5 hours.



If they work together, what is the missing value from the table that represents the part of the project Dominik will complete?

Respuesta :

Answer:

The part of the project Dominik will complete when they work together

= (5/8) of the entire work.

Have a good day!