Suppose operation X feeds directly into operation Y. All of X's output goes to Y, and Y has no other operations feeding into it. X has a design capacity of 80 units per hour and an effective capacity of 72 units per hour. Y has a design capacity of 100 units per hour. What is Y's maximum possible utilization

Respuesta :

Answer:

72 percent

Explanation:

The computation of the Y's maximum possible utilization is given below:

In the case when the maximum output received from C is 72 units per hour so the maximum input rate to Y should also be 72 units per hour as X and Y are linked in series

So as per the given situation, Y's maximum possible utilization is 72 percent