We have created the following Planned Production Orders over the planning period: 150 Product A We have the following Raw Materials on hand and available to be dedicated to these Planned Production Orders: Enough Raw Materials to product 90 Product A There are Purchase Orders at our suppliers for the following Raw Materials: 20 Product A
How many products should we order on New Purchase Orders with our suppliers?

Respuesta :

Answer: 40 products

Explanation:

There is a need to produce 150 products.

There is enough materials to produce 90 products out of this 150.

There are purchase orders for materials for 20 more products out of this.

Number of products that should be ordered is the remaining figure:

= 150 - 90 - 20

= 40 products

The number of products that should be ordered is 40 products on the new purchase orders with our suppliers. This is part of a planned production order.

What do you mean by planned production?

Production planning is the planning of production and manufacturing modules in a company or industry.

As per the question, there is a need to produce 150 products and there are enough materials to produce 90 products out of these 150.

We have purchase orders for materials for 20 more products out of this.

Therefore, the number of products that should be ordered is the remaining figure:

[tex]\rm\,Number \;of \; Products \;that \; should \;be \;ordered = 150 - 90 - 20\\\\\\rm\,Number \;of \; Products \;that \; should \;be \;ordered = 40 \;products[/tex]

Hence, the number of products that should be ordered is 40 products.