Total overhead applied = $220
Explanation:
Total variable overhead estimated = Variable manufacturing overhead per machine-hour * Total machine-hours
Total variable overhead estimated = ($2 * 32,700)
= $65,400
Total overhead estimated = Total variable overhead estimated + Total fixed overhead estimated
Total overhead estimated = $65,400 + $294,300
Total overhead estimated = $359,700
Predetermined overhead rate = Total overhead estimated / Total machine hours
= $359,700 / 32,700
=$ 11 per machine hour
Hence, the total overhead applied = Predetermined overhead rate * Total machine hours L716
Total overhead applied = ($11 * 20)
Total overhead applied = $220