Answer: The answer is below...
Explanation: Answer a. Order Quantity = √2RO/C = √2 * 25750 * 250 / .33 * 10 = √1975.23 From the standard normal distribution, z = 1.64 = (515 * 1) + (1.64 * 25) = 556 Reorder point = Lead time * daily usage = 7 * 25 = 150 per week Answer b. Holding cost = Q/2 (H) = 1975/2 (.33)10 = $3,258.75 Ordering cost...