Answer:
$ 27.10
Explanation:
Given
The direct labor budget 5,800
Variable overhead rate is $9.10 per direct labor-hour.
Variable Overhead = 5800* $ 9.1= $52780
Budgeted fixed manufacturing overhead is $104,400
Total Budgeted Overhead = $ 157180
Budgeted Labor Hours 5800
Predetermined Overhead rate = $ 157180/ 5800= $ 27.10
The predetermined overhead rate is calculated by dividing the total budgeted overhead by the budgeted hours.
The total budgeted overhead includes the variable overhead and the budgeted fixed overheads.