As a financial analyst, you are tasked with evaluating a capital-budgeting project. You were instructed to use the IRR method, and you need to determine an appropriate hurdle rate. The risk-free rate is 4%, and the expected market rate of return is 11%. Your company has a beta of 1.0, and the project that you are evaluating is considered to have risk equal to the average project that the company has accepted in the past.
Required:
1. According to CAPM, the appropriate hurdle rate would be ___________.