Answer:
b. all project risks should be eliminated before the project charter is signed.
Explanation:
Option b is correct, as there is no way to eliminate all project risks before signing the project charter.
It is necessary for project managers and teams to consider the risks and include them in the project regulations, but this alternative is incorrect because the risks constitute a set of events that can be threats or opportunities that may arise throughout the project, and influence its progress positively or negatively.