The total completion time on a project is 25 days. Task A is planned to take seven days while Task B is planned for five days and Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have?
A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 17 days slack.
D) Positive 3 days slack.