During the reporting period ending 30 June 2022, Midnight Boil Limited constructed a nuclear power generator just outside of Melbourne. The cost of the power generator and associated technology amounted to $13350000. Other costs associated with the construction amounted to ________. $ Costs incurred in obtaining access to the site2580500 Power permits480500 Engineers' fees1180500 4241500 The plant was ready to start generating power on 1 July 2022, with actual generation starting on 1 October 2022. At the end of the power plant's useful life, which is expected to be 10 years, Midnight Boil Limited is required by government to dismantle the plant, remove it and return the site to its original condition. After consulting its own engineers and environmentalists, Midnight Boil Limited estimates these costs to be: $ Dismantling the plant830500 Environmental remediation costs1329500 Replacement of flora and fauna110000 2270000 Midnight Boil Limited uses a discount rate of 9 per cent. REQUIREDPrepare the journal entries necessary to account for the power plant for the years ended 30 June 2022, 30 June 2023 and 30 June 2024. Ignore depreciation. (Round your answers to the nearest whole amount.)