Given the project is the top goal in the strategic plan for your department and 50% of the contract cost has been spent, which decision would you make and why?
a) Continue with the project to fulfill strategic goals
b) Suspend the project to assess risks and costs
c) Terminate the project to cut losses
d) Review the project's progress before making a decision