On the 7th day of the iteration, the team realizes they cannot complete their 5 out of 13 stories. What should the Product Owner do?
a) Extend the iteration to complete all the stories. b) Remove the incomplete stories from the iteration. c) Add the incomplete stories to the next iteration. d) Reduce the scope of the remaining stories.