It is currently July 10, the 10th day in the production calendar of the Machine Shop. Three orders (A, B, and C) are to be processed at a particular machine tool. The orders arrived in the sequence A-B-C. The table below indicates the process time remaining and production calendar due date for each order. Determine the sequence of the orders that would be scheduled using the following priority control rules: (a) first-come-first-serve, (b) earliest due date, (c) shortest processing time. Determine which jobs are delivered on time and which jobs are tardy (status of each order). JULY 2020 AUGUST 2020 Remaining process time Due date 4 days Day 20 16 days Day 30 С 6 days Day 18 T (a) FCFS (first-come-first-serve) Order Start date Completion Order Start date Completion Start date Completion (b) EDD (earliest due date) (c) SPT (shortest processing time) Order F Status Status Status