What is the MAXIMUM amount of a lien that can be claimed by a subcontractor who notifies the lien agent for a two-family residential property on August 1 that the subcontractor first provided labor and materials on the project on May 1? The subcontractor billed the general contractor for $4,000 per month, through September 30, and was never paid.